Ontario
Police Department Headquarters
Ontario,
California |
- This
project involved the renovation of the former FEDCO in Ontario,
California. This project called for the complete interior
demolition and renovation of the existing building to meet
the Police Department needs
which includes, a new Department of Corrections approved holding
facilities, six bureaus, new regional dispatch center, community
meeting
facilities, Police Museum, and indoor range. Renovated parking
for 840 stalls, lighting, and landscaping improvements were
also needed. The project schedule for the new Police Department
Headquarters involved six months for design,
and
approvals through
construction contracting and 12 months for the renovations
and improvements.
- Client
Contact: Otto Kroutil, City of Ontario
- Construction
Cost: $11 Million
- Project
Construction Time Frame: March 2003 - January 2004
- Architect:
Carrier Johnson
|
| |
|